County list of additional conditions
County | Additional conditions 1-A1 | Additional conditions 1-A2 | Additional conditions 1-C2 |
---|---|---|---|
Adams | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Ashland | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Barron | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Bayfield | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Brown | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Buffalo | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Burnett | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Calumet | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
Chippewa | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Clark | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Columbia | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | ER Review required. | ER Review required. |
Crawford | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Dane | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
ER Review required. | ER Review required. |
Dodge | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
Door | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
Douglas | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Dunn | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Eau Claire | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Florence | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20th and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Fond du Lac | No additional conditions. | No additional conditions. | No additional conditions. |
Forest | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Grant | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Green | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
Green Lake | No additional conditions. | No additional conditions. | No additional conditions. |
Iowa | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. |
If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Iron | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Jackson | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Jefferson | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
Juneau | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Kenosha | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
Kewaunee | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
La Crosse | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Lafayette | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
Langlade | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20th and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Lincoln | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Manitowoc | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
Marathon | For work on structures five or more stories in height, work shall not be conducted between March 1st and July 31st. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Marinette | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Marquette | No additional conditions. | No additional conditions. | No additional conditions. |
Menominee | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Milwaukee | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
Monroe | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20th and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Oconto | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Oneida | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Outagamie | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Ozaukee | For work on structures five or more stories in height, work shall not be conducted between March 1st and July 31st. | No additional conditions. | No additional conditions. |
Pepin | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
Pierce |
For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Polk | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Portage | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Price | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Racine | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
Richland | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional comments |
Rock | No additional conditions. | ER Review required. | ER Review required. |
Rusk | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Sauk | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
ER Review required. | ER Review required. |
Sawyer | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Shawano | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Sheboygan | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | No additional conditions. | No additional conditions. |
St. Croix | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Taylor | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | No additional conditions. |
Trempealeau | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Vernon | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. |
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. |
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Vilas | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Walworth | No additional conditions. | No additional conditions. | No additional conditions. |
Washburn | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Washington | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. | No additional conditions. |
Waukesha | No additional conditions. | No additional conditions. | No additional conditions. |
Waupaca | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Waushara | No additional conditions. | No additional conditions. | No additional conditions. |
Winnebago | For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |
Wood | No additional conditions. | If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. | May not occur during the turtle nesting and incubation period (May 20 through Sept. 18). |