Skip to main content

County list of additional conditions

 

County Additional conditions 1-A1 Additional conditions 1-A2 Additional conditions 1-C2
Adams No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Ashland For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Barron No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Bayfield For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Brown For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Buffalo For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Burnett No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Calumet Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. No additional conditions.
Chippewa No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Clark No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Columbia For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. ER Review required. ER Review required.
Crawford Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Dane Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
ER Review required. ER Review required.
Dodge Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. No additional conditions.
Door Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. No additional conditions.
Douglas Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Dunn No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Eau Claire No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Florence Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20th and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Fond du Lac No additional conditions. No additional conditions. No additional conditions.
Forest No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Grant Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Green Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. No additional conditions.
Green Lake No additional conditions. No additional conditions. No additional conditions.
Iowa Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.

Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Iron Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Jackson Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Jefferson For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. No additional conditions. No additional conditions.
Juneau Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Kenosha For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. No additional conditions. No additional conditions.
Kewaunee For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. No additional conditions. No additional conditions.
La Crosse Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Lafayette Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. No additional conditions.
Langlade No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20th and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Lincoln No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Manitowoc Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. No additional conditions.
Marathon For work on structures five or more stories in height, work shall not be conducted between March 1st and July 31st. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Marinette For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Marquette No additional conditions. No additional conditions. No additional conditions.
Menominee No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Milwaukee For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. No additional conditions. No additional conditions.
Monroe Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20th and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Oconto No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Oneida No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Outagamie For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Ozaukee For work on structures five or more stories in height, work shall not be conducted between March 1st and July 31st. No additional conditions. No additional conditions.
Pepin Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. No additional conditions.
Pierce

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.

Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Polk Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Portage No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Price No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Racine For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. No additional conditions. No additional conditions.
Richland Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. No additional comments
Rock No additional conditions. ER Review required. ER Review required.
Rusk No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Sauk Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
ER Review required. ER Review required.
Sawyer No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Shawano No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Sheboygan For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. No additional conditions. No additional conditions.
St. Croix Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Taylor No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. No additional conditions.
Trempealeau Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Vernon Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31.
Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year.

If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18.
May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Vilas No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Walworth No additional conditions. No additional conditions. No additional conditions.
Washburn No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Washington Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. Below-ground excavation beyond five feet in depth shall not occur from October through April. Also, it does not include below-ground or surface-level excavation at known entrances to bat hibernacula at any time of year. No additional conditions.
Waukesha No additional conditions. No additional conditions. No additional conditions.
Waupaca No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Waushara No additional conditions. No additional conditions. No additional conditions.
Winnebago For work on structures five or more stories in height, work shall not be conducted between March 1 and July 31. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).
Wood No additional conditions. If within 200 feet of a creek, stream or river, work shall not be conducted between May 20 and Sept. 18. May not occur during the turtle nesting and incubation period (May 20 through Sept. 18).